NSW Department of Industry

Levels 43, 48 & 49, MLC Centre, 19 Martin Place, Sydney
Office fit-out
14 weeks
Woods Bagot, GWA Consultants, ER&D Pty Ltd, Wood & Grieve Engineers
Lump sum contract
4,500m2

Works comprised strip out of approximately 85% of the existing fit-out; multiple new office, meeting and reception environments; full services upgrades; extensive joinery (cabinetry, framing and stairs) and workstations and furniture packages.

With only enough “swing space” to relocate one floor at a time, works were meticulously programmed to ensure strip out and new fit-out works to each of the 1,500m2 floor plates were completed within a 4.5 week per floor timeframe.

Various kitchens, interview, V/C and meeting rooms remained fully accessible and operational throughout the works.